[10/07]
Sunday morning, before our houseguests arrived... this was our kitchen.
[10/08]
As of Monday night, cabinet work on the left side is well underway.
Nothing has changed on the right side yet.
[10/09]
Tuesday night, the lower cabinets went in on the left side while
demolition began on the right side.
[10/10]
By Wednesday night, most of the electrical work was done as are the
cabinets on the left side. The right side has been cleared now.
[10/11]
No more changes to the left side, but not all the cabinets,
refrigerator, and dishwasher are in on the right side.
[10/12]
Friday night, around 9:30PM, the counter tops were finished and
the sink is in place (but not hooked up). And the refrigerator is
now producing delicious cold filtered water!
[10/13]
Saturday was a mall-shopping day, and then we all went out to dinner.
In between though, we managed to finish up the plumbing; the dishwasher
and sink are ready for use! The paper towels there are checking for
leaks.