[10/14]
As of Sunday night, after one week, all the cabinets have doors...
but no doorknobs... yet!
[10/16]
As of Tuesday night, you can see that the trim beneath the cabinets
is finished and, behind the stove, wall tiling has begun. Also,
some handles are starting to appear on the cabinets!
[10/18]
As of Thursday night, you'll notice that all the trim along
the top of the cabinets is in place. This was made more difficult
since our ceiling isn't exactly level... each piece of wood had to be
cut to size. Also, all the handles are installed!
[10/19]
The rest of the wall tile was put in place on Friday.
The big decision was whether or not to run tile up along the
window. Looks like Catarina made the right decision!