[10/21]
As of Sunday night, after two weeks, the tile against the back wall
has been grouted and the under-cabinet and above-sink halogen lights
have been installed. We also centered the lighting fixture, accounting
for the big hole in the ceiling.
[10/23]
The rest of the tile grout went in on Monday, as did the switch
plates on the GFCI wall plugs. By Tuesday night, the hole in the
ceiling had been patched and the back wall had a smoothing paper
glued over it to make way for a new coat of paint (the color
you see here is the paper, not the final color). And a new
toaster oven appeared on the counter above the dishwasher!
[10/25]
The walls have been painted, the ceiling fixture is in place,
and the gap between the tile/counter has been caulked...
It's FINISHED!!!!!! :-)